"Great customer service. The folks at Novedge were super helpful in navigating a somewhat complicated order including software upgrades and serial numbers in various stages of inactivity. They were friendly and helpful throughout the process.."
Ruben Ruckmark
"Quick & very helpful. We have been using Novedge for years and are very happy with their quick service when we need to make a purchase and excellent support resolving any issues."
Will Woodson
"Scott is the best. He reminds me about subscriptions dates, guides me in the correct direction for updates. He always responds promptly to me. He is literally the reason I continue to work with Novedge and will do so in the future."
Edward Mchugh
"Calvin Lok is “the man”. After my purchase of Sketchup 2021, he called me and provided step-by-step instructions to ease me through difficulties I was having with the setup of my new software."
Mike Borzage
October 09, 2026 2 min read

Demolition in Revit is not the same as deleting. To document renovations accurately, model the element that exists today, assign it to the correct existing phase, and then mark it for removal in the appropriate future phase. This preserves the project’s history and lets Revit produce reliable existing, demolition, and proposed documentation from one coordinated model.
Start by reviewing Manage > Phases. A typical renovation project includes:
For an element to be demolished correctly, its Phase Created must occur before its Phase Demolished. For example, an existing partition wall should have:
Do not erase the wall from the model simply because it will be removed. Deleting it eliminates useful information from existing-condition views, can disrupt room boundaries, and prevents demolition plans and schedules from reporting it accurately. Instead, select the element and assign its Phase Demolished in the Properties palette.
Next, control how that information appears through view phasing. Every plan, section, elevation, and schedule should be reviewed for its Phase and Phase Filter. A dedicated demolition plan commonly uses a phase filter that shows previous construction together with demolished elements. This makes the elements being removed visible while maintaining enough existing context for contractors to understand the scope.
When replacing an item, model both conditions. For instance, an existing door that will be removed should remain in the model with a demolition phase assigned. Place the replacement door as a separate element created in New Construction. The same principle applies to walls, windows, casework, ceilings, plumbing fixtures, and other renovation scope.
Be careful with elements that are hosted by other elements. Demolishing a wall may affect hosted doors, windows, inserts, wall sweeps, and room separation behavior. Review dependent components and confirm whether they should also be demolished, retained, or recreated in the new phase. This extra check prevents incorrect schedules and avoids unexpected gaps in proposed views.
Finally, standardize demolition graphics in Manage > Phases > Graphic Overrides rather than applying individual overrides in each view. Centralized settings reduce coordination errors and make drawing output easier to audit. For Revit software, training, and workflow resources, visit NOVEDGE’s Revit collection and explore additional BIM tools at NOVEDGE.
You can find all the Revit products on the NOVEDGE web site at this page.